🏗️ Live Construction Updates
New Building Progress
Track milestones for the new facility build.
Project Timeline
April 2026 — February 2027
Today
Aug 29, 2026
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
2
2
Apr 2026 You are here · 45% throughFeb 2027
Building Contract signed with EEC to startApr 27, 2026
Completed
Overhead Cranes Ordered with DepositApr 27, 2026
Completed
Building submitted to state for permitMay 27, 2026
Completed
Specialty Foundation onsite for piersJun 22, 2026
Completed
EMX starting excavation of foundationJun 22, 2026
Finished
Fleury starting footings and wallsJun 29, 2026
Finished
Building being delivered (4 trucks)Jul 7, 2026
Finished
Floor being pouredJul 30, 2026
Completed
Massive Erection DayAug 17, 2026
Started
Radiant Floor Heat TubingJul 28, 2026
Completed
Crane Rail Installation StartedAug 24, 2026
Started
Windows Installed along with Internal FramingAug 27, 2026
Started